Auditor: State construction projects ran late and over budget
Workers complete the Vermont Psychiatric Care Hospital in Berlin before its opening in 2014. File photo by Roger Crowley/for VTDiggerMajor state construction projects went over budget and missed deadlines, sometimes by several years, according to a new report by the state auditor.
The report also says the reasons for those delays and excess expenses are unclear because the Department of Buildings and General Services lacked an adequate tracking system.
The auditor’s office reviewed 10 cons