An early look at the Bellevue light-rail tunnel
Employees and machines from Atkinson Construction finished digging Sound Transit’s future light-rail tunnel in Bellevue this week from East Main Street to Bellevue Downtown Station next to City Hall. They scoured and reinforced in 4-foot-long sections, advancing 2,000 feet over 15 months — five months ahead of schedule. This tunneling method differs from the usual boring […]