Speedy HS2 viaduct push cuts disruption for drivers

HS2 engineers completed the final operation to move two railway viaducts into place over the M42/M6 link roads in North Warwickshire more than six hours ahead of schedule this weekend.
The ‘push’ to move the 158-metre-long West Link Viaduct into its final position over both westbound and eastbound motorway link roads took a total of 11 hours.
Main works contractor Balfour Beatty VINCI (BBV) completed the work quicker than planned allowing the motorway link roads to be reopened 6.5 ho