17-10-2024 08:45 via constructionenquirer.com

Piling starts on HS2 Curzon Street Station

Work has started on the installation of 2,000 piles for the foundations of Birmingham’s Curzon Street Station which will be the city’s HS2 rail hub.
Work is being led by main contractor Mace Dragados Joint Venture (MDJV) and piling specialist Keltbray.
A team of 80 people are delivering the foundations work using three 95 tonne, 30-metre-tall piling rigs on the site.Piling is planned to be completed by mid-2025, with the installation of further foundations on top of the piling starti