21-10-2024 08:41 via constructionenquirer.com

Cost-row Cambridge road closed as cracks appear

Parts of a new £32m bypass and bridge in Cambridge have been closed after cracks appeared.
Engineers are now monitoring the King’s Dyke Crossing at Whittlesey which is being affected by movement in the main embankment which supports the crossing.
The bridge opened in 2022 and was originally due to be built by Kier but the firm walked away from the job in 2019 after failing to agree a price for the project after raising concerns about ground conditions.At the time Kier spokesperson sa