Nottingham Post published Delayed Ilkeston railway station needs £500,000 of...

The delayed Ilkeston railway station needs another £500,000 of council taxpayers' money to be built, it has been revealed.But a start date for work to begin has finally been pencilled in with work set to begin next month. Building work on the station, which should have been opened to passengers last December, has yet to begin after long delays caused by flooding concerns and the discovery of great-crested newts at the site.The latest projection for the final cost has been increased to...