Crossrail requires final £150 million to complete the Elizabeth line
The Crossrail project is still going to require a final injection of around £150 million to complete the railway, the latest TfL figures have confirmed.
The Crossrail project’s current funding authorisation is for £15,789 million, and it had spent £15,479 million up to 8th January 2022, leaving it some £310 million in the pot that can be spent.
However, TfL’s Investment Programme Report, published ahead of the Programmes and Investment Committee yesterday, is