The Site C showdown: How much would it cost to kill it?
If John Horgan really does slam the brakes on the Site C dam, it will be the most expensive stop-work order in B.C. history.
That’s because B.C. Hydro has already spent $1.75 billion on the dam and continues to spend $60 million a month on the province’s biggest-ever public-sector construction project.
That’s $2 million a day. Or $83,333 an hour. Or $1,388 a minute. The dam will probably cost you another 7,000 bucks or so by the time you finish reading this. Any way you add it
Read more »