21-01-2019 12:30 via ottawacitizen.com

Ottawa LRT documents reveal settlement, spills and stains

Here are some of the gaffes highlighted in inspection or non-conformance reports regarding the city’s Confederation Line LRT project.At Lyon Station, inspectors in 2017 realized 19 “sleeves” for future mechanical installations weren’t embedded in a concourse slab. It was missed since the mechanical subcontracts hadn’t been awarded before the construction, a non-conformance report says.
At Rideau Station, inspectors in 2017 found water-stop membranes flooded after wo
Read more »