Hydro will be 'burned' if Site C is suspended or cancelled

VICTORIA — B.C. Hydro would face payouts of more than $1 billion to cancel or suspend the Site C project, according to an independent review for the B.C. Utilities Commission.
The Crown corporation would also have to discount or write off the more than $2 billion already spent building the giant hydroelectric dam on the Peace River, before starting from scratch to seek alternatives.
Those and other considerations loom large going into next week as the utilities commission prepares to