Trans Mountain says 'worst-case' could see pipeline completion delayed to end of 2024
The Crown corporation behind the Trans Mountain pipeline expansion says it may not complete the project before December 2024 if a regulator does not approve its request for a route deviation. Trans Mountain Corp. says the new time frame is a worst-case scenario that could add close to $86 million in cost overruns to the final project price tag. Trans Mountain Corp. had hoped to have the pipeline in service in early 2024 but has run into engineering difficulties related to the drilling of a tunne