12-08-2022 08:35 via hamilton.ca

Lane restrictions on a portion of Mud Street W beginning on Monday

HAMILTON, ON – To safely complete road resurfacing on the south side of Mud St W, the City of Hamilton will reduce Mud St W to a single lane in each direction between Isaac Brock Dr and Upper Centennial Pkwy beginning Monday, August 15 for approximately five weeks.The work on the south side of Mud St W is expected to wrap up on or before September 12, 2022. Once work is completed on the south side, crews will shift work onto the north side of Mud St.
Read more »