Work on Chatham-Kent Hub on schedule and budget

Construction of the new Chatham-Kent Community Hub is on track and on budget, a report that went to council Monday says. The project at the former Sears building in downtown Chatham began construction in December and is 22 per cent complete as of July 21, the report by Edward Soldo, infrastructure and engineering services general manager, said. The contract has so far been reduced by $8,327 through two change orders “that have provided a credit to the original contract,” the report