Downtown Revitalization Project update: Aug. 31 to Sept. 4
The downtown revitalization project continues through the week of Aug. 31 to Sept. 4.Underground infrastructure installation and road construction continue on Icomm Drive. Deep sanitary sewer installation is complete, with storm sewer and watermain work now underway. Temporary traffic changes will take effect Sept. 1 to support ongoing construction. The closure of Icomm Drive is expected to continue until the end of September. The following temporary traffic changes will be in place beginning S